Projects

Candidate capital projects with deterministic metrics at the mean of each uncertain input. A point NPV hides the risk — see the Risk tab for the distributions.

ProjectCapitalNPVIRRPayback PIMIRR
plating-line
New plating line · 5 yr
500 103 0.177 3.1 yr 1.21 0.142
robot-cell
Robotic work cell · 5 yr
400 121 0.210 2.9 yr 1.29 0.158
power-upgrade
Electrical service upgrade · 5 yr
100 -46 -0.098 0.55 -0.024
tank-monitoring
Tank-monitoring retrofit · 7 yr
150 67 0.225 3.4 yr 1.44 0.159
paint-booth-east
Paint capacity — east line · 6 yr
350 57 0.153 3.8 yr 1.16 0.128
paint-booth-west
Paint capacity — west line · 6 yr
350 68 0.162 3.7 yr 1.19 0.132
emissions-scrubber
Emissions scrubber (compliance) · 8 yr
200 -194 -0.383 0.04 -0.256
specialty-coating-line
Specialty-coating line · 6 yr
650 281 0.227 3.1 yr 1.40 0.163

IRR shows — when a stream has no single real internal rate (MIRR is the robust alternative). Every input carries an uncertainty range; the Monte Carlo on the Risk tab turns these points into distributions.